How long does a resin floor take to cure?

Installation. By ASP Technical Team, updated

The short answerAt 20°C, ASP's solvent-free epoxy floors take light foot traffic after 16 hours, light traffic after 24 hours and heavy duty traffic after 48 hours, with full chemical cure at 7 days. ASP's polyurethane floors take light traffic after 24 hours and heavy duty traffic after 48 hours, with full chemical cure at 7 days.

How soon you can use a new floor depends on the resin, the system and the temperature. All the times below are measured at 20°C. Cooler conditions slow curing; check with ASP's technical team before installing in cold or hot weather.

Cure times by product

ProductLight foot trafficLight trafficHeavy duty trafficFull chemical cure
ASP-coat500, ASP-coat1000, ASP-coatSL16 hours24 hours48 hours7 days
ASP-screedPTS, ASP-screedSTB16 hours24 hours48 hours7 days
ASP-coatWBE–24 hours24 hours (full traffic)7 days
ASP-creteSL, ASP-creteMD, ASP-creteRT, ASP-creteSR–24 hours48 hours7 days
ASP-coatPU–24 hours24 hours7 days
ASP-chemVE-H, ASP-chemVE-V–24 hours48 hours7 days

Working time

Working time is how long the mixed material stays usable. At 20°C it is 15–20 minutes for the solvent-free epoxies, 10–15 minutes for the polyurethane cement floors and around 35 minutes for the water-based ASP-coatWBE. Mix only what can be applied in that window.

Between coats

For ASP-coat500, a second coat can go on after 10 hours but no later than 24 hours after the first. ASP-coatWBE's second coat must go on within 24 hours of the first.

What full chemical cure means

A floor can carry traffic well before it reaches full chemical resistance. Keep chemical spillages and aggressive cleaning off the floor until the 7-day full chemical cure is reached.

Need the area back faster?

Where downtime has to be kept to a minimum, ASP's MMA rapid cure systems and the fast return to service of ASP-creteSL and ASP-creteMD in refurbishments can help. Talk to our team about your programme.

Frequently asked questions

How long before I can walk on a new epoxy floor?

ASP's solvent-free epoxy floors take light foot traffic after 16 hours at 20°C.

When can forklifts drive on a new resin floor?

Heavy duty traffic can use ASP's epoxy and polyurethane cement floors after 48 hours at 20°C.

How long does a resin floor take to fully cure?

Full chemical cure takes 7 days at 20°C for ASP's epoxy, polyurethane and vinyl ester floors.

How long is the working time of an epoxy floor coating?

At 20°C, ASP's solvent-free epoxies have a working time of 15–20 minutes once mixed.